Concrete
- What Is concrete?
- Definition: Concrete is a mixture of portland cement, aggregate and water that is mixed wet, formed, and dries to a permanently hard and strong material.
- History
- Thought to have been used in 3000 B.C. in core of pyramids
- Supposedly invented by the Romans in 200 B.C.
- Not used extensively until the late 19th century.
- Reinforced concrete (using steel reinforcing bars) invented in 20th century.
- Frank Lloyd Wright was one of first architects to use reinforced concrete in Untiy Temple, Oak Park, built in 1908.
- Uses of concrete in buildings
- Footings
- Foundation Walls
- Slab-on-grade
- Basement floor slabs
- First floor slabs
- Garage floor slabs
- Columns
- Beams
- Retaining walls to hold back earth embankments to keep from eroding or washing away the soil
- Structural slabs
- Structural walls
- Stairs
- Paving (sidewalks, driveways, or roads)
- Floor fill over concrete structural slabs to bury piping or electrical conduit or to level floors, usually made of light weight concrete
- Roof fill over concrete structural slabs to provide a slight slope for flat roofs to drain usually made of light weight or insulating concrete
- Swimming pools
- Precast concrete slabs, walls, etc.
- Concrete masonry units
- Finish flooring (terrazzo)
- Ornamental uses
- Stoops
- Chimney caps
- Concrete structural condition types
- Plain (no reinforcement)
- Reinforced (includes steel "re-bars")
- Prestressed (tensile stress is imposed on reinforcing prior to concrete setting up)
- Post-tensioned (tensile stress is imposed on reinforcing after concrete has set up)
- Concrete Strength
- Factors which determine strength
- Water-cement ratio, measured in gallons of water per sack of cement - the less water used per sack the stronger the mix
- one sack of cement weighs 94 pounds
- minimum water required for "hydration" (the chemical reaction which solidifies cement) is 3 ½ gallons per sack, but more water is required to produce "workability" of the mix.
- Super-plasticizers can be added to increase workability without affecting the water-cement ratio
- Curing
- Age
- ½ strength in 3 days
- Initial set after 2 to 3 hours
- full strength at 28 days
- Importance of strength
- Structural elements (columns, beams and slabs) are sized based on their expected strength - the stronger the concrete, the smaller the structural element can be.
- Testing
- Performed by an independent testing agency for every "batch" of concrete
- Compression tests - three 6" diameter x 12" long "cylinders" of concrete are taken at time of delivery of concrete for each batch
- Slump tests are also made at time of delivery - this tests how "stiff" the mix is and can be compared against other batches to be used in the same building to monitor consistency of the mixes.
- Materials which make up concrete
- Portland cement
- Aggregate
- Fine - sand
- Coarse - gravel
- Light weight aggregates - expanded slag or shale
- Water - potable
- Admixtures
- Air-entraining
- Super-plasticizers
- Accelerators (for use in winter)
- Retarders (for use in summer)
- Density
- Normal weight: 150 pounds per cubic foot
- Light weight: 110 pounds per cubic foot
- Mixing Concrete
- Types of mixing plants
- Batch plant at site
- Ready-mix plant - concrete delivered to job site in agitator trucks
- Measurement of materials
- Water measured by volume
- Cement measured by weight
- Aggregate measured by weight
- "Well proportioned" mix
- Formwork
- Types
- Constructed formwork
- Slip forming
- "In situ"
- Materials
- Wood
- Boards
- Plywood
- Metal
- Fiberglass
- Earth
- Form-release agents
- Bracing
- Form ties
- Shoring and re-shoring
- Reuse of formwork
- Placing Concrete
thumb is 2 x the slab thickness (in feet), thus a 4" thickl slab needs control joints every 8 feet in both directions.
- Clean and level subgrade
- Weather precautions
- Do not pour flatwork in rain
- Do not pour concrete on frozen substrates
- Do not pour in exceptionally hot weather
- Place reinforcing bars and secure to formwork
- Place concrete in "lifts" of 6" to 20" high
- Continuously pour, do not leave off work without providing a bulkhead
- Spading and vibration - do not over-vibrate to prevent segregation
- Construction joints - key in joints where pour is finished for the day
- Control joints in slabs to control shrinkage about every 8 feet (rule of
- Finishing concrete slabs
- Screeding
- Darbying or "Floating"
- Edging
- Wood floating
- Troweling
- steel trowel for normal concrete
- Aluminum or magnesium trowel for air-entrained concrete
- Specialty finishes
- Brooming for sidewalks and driveways
- Exposed aggregate
- Staining
- Impressing
- Curing
- Continuous fine water spray
- Soaked burlap
- Soaked straw
- Coating with cure and seal spray-on chemical
- Sealing